Construction Updates
Monday June 6, 2010
PSA
Re: Temporary Parking at Aztec District Court Courthouse
For Immediate Release
The 11th Judicial District Courthouse in Aztec located at 103 South Oliver in Aztec, is undergoing an expansion and remodel. As part of this process, beginning June 22 the public parking lot will be under reconstruction for approximately four to six weeks.
Persons visiting the courthouse should park in the San Juan County Administration parking lot, then follow the signed walkway across South Oliver to the courthouse.
Disabled persons are encouraged to call 334-6151 for assistance in getting from the temporary parking area to the courthouse. A wheelchair will be made available by court employees to assist as needed.
We are sorry for this temporary inconvenience but are confident you will be proud of its results for our community.
Friday Feb 26,2010
The Juror and Employee parking lot are closed. The Public Parking lot is going to be way crowded. You can park in the County parking lot across Oliver St Just be careful crossing back over to the courts.
Friday Feb 19, 2010
All Foundations have been poured waiting on the concrete to set.
Friday Feb 12, 2010
.They will be Doing the work for pouring the foundation next week
Sunday Feb 7, 2010
Power line repaired.
Monday Feb 1, 2010
Power outage rescheduled for this friday Feb 5, 2010 at 5:0pm.
Thursday Jan 28, 2010
Nevermind rescheduled do to weather
Monday Jan 25, 2010
Power outage scheduled for this friday Jan 29, 2010 at 5:0pm shouldnt affect much tho.
Monday Jan 11, 2010
Huge Power outage. a trackhoe driver hit an unmarked main power line for District court. Power was out for a total of 5 hrs. The I.T. guy was able to get a small generator to run all the computer stuff so that Aztec Mag and both Farmington District Court locations could still operate. GO I.T. GUY.
Thursday Jan 8, 2010
After an extended break in construction due to gas and water line issues; construction has resumed.
1. Over the next two weeks construction will be louder next to the building again due to excavation work. Once that is done, they will start working on the concrete.
2. The next minor disruption will be the storm drain installation which will temporarily impact the Juror parking in the back.
Thursday Jan 7, 2010
Another water outage.
Friday Dec 18, 2009
Construction is pretty much done for the holidays they be on it hot and heavy starting Jan 4, 2010.
Snow on the ground not much construction gonna happen today
Friday Dec 11, 2009
Gas and heat is out. They are moving the gas lines out of the way for the construction. it is dang cold in here!!!!!
Monday Dec 7, 2009
Snow on the ground not much construction gonna happen today
Wednesday Dec 2, 2009
They shut the water off today for about an hour.
Monday Nov 30, 2009
the old main entrance is completely gone
Wednesday Nov 25, 2009
We are live with the new Temp Main entrance. It has no windows please be careful going in and out.
Wednesday Nov 18, 2009
Changing main entrance to the temporary main entrance. Should be finished about next Wednesday
Monday Nov 9, 2009
Construction has started!! more to follow